Sunday, November 30, 2014

Vinyl siding and shutters

The vinyl siding is done 😄



Porch 
:)
You can see the boys' school from the front door, I love that it is walkable distance. 
 







Thursday, November 27, 2014

Floors!! And so much more!

This week they completed the floors!! And we saw a lot of other changes as well. 
Here is a sneak peak :
They had the floors covered to finish the other work. They look amazing!!! I have been waiting to see how it would look ever since we picked out the hardwood floors.

We did the entire first floor with hardwood floors. Main reason, carpet + kids = scary. 


Next favorite: granite counter top!!! 
It goes perfectly with the caninet color. Our sales associate at the design center was very helpful in picking out our options. We had so many to choose from. 
The backslash.. 
They also put in all of the light fixtures

Finally the vinal siding: 
They weren't able to complete it because is the weather but it's coming together really well!! 



Sunday, November 23, 2014

Fireplace, paint, tiles

This week we saw that they started on the tiles in all the bathrooms 
Master bathroom shower 
A little accent :)
12 inch tiles which were an upgrade 
Tiles in the basement bathroom. I think this was a smaller upgrade. 
tiles in the boys bathroom. 
Fireplace
A little fun with Andrew. 😃
My double oven!! I am so excited to see it :)
Another favorite of mine, the front porch. They also added the brick. 
Drew admiring his new home :)

So, I think they will start working on the vinal siding, we saw the matrial outside. I...or we chose a really light yellow color for the vinal siding. I always wanted a yellow house. The door will be a dark green. We chose all the colors in August so my memory is a bit foggy. I love that Ryan Homes (builders) allows us to pick the colors, they have a huge variety. 

More next week! 










Monday, November 17, 2014

Cabinets, dry wall, paint, molding and doors


This week they started putting in cabinets . 
Kitchen 

Close up

Me...lol
Boys' bathroom 
Master bathroom 
Basement full bathroom. We went with the standard cabinets for the three bathrooms. 

Railing will be stained to match the hardwood floors on the main floor. The stairs will have carpet. 
Upstairs hallway. 

The space for the double oven :) 
View from the livingroom
View from the morning room. 












Sunday, November 9, 2014

Walls!!

So this week they started the dry wall!
This is from the morning room looking into family, dining and living room. 

 Front door


 There will be a front porch. Probably one of my favorites! 


Andrew!! 

Upstairs bedroom

Recess lighting in the kitchen. 


Every week the house looks different. It's so crazy for fast the house is coming along. 

Here are a few pictures of the neighborhood. 
Our street name: Winning Glory drive. Not even on the map yet! 

The elementary school that the boys will go to. It's just up the street. 

Can't wait for next week! 








Sunday, November 2, 2014

Wiring and HVAC (heating, ventilation, air conditioning)

Last week the roof was finished, the wiring was done and the HVAC were installed. 

Also, on Friday we had our pre drywall meeting. This meeting focuses on what is it that goes inside the walls before the drywall goes up. Also, at this point they were able to tell us when our closing date will be, which is December 26th!! :) 

We also locked in our interest rate with NVR mortgage. We were able to lock it in at 3%. 

Here are some pictures.. 

Finished roof. 

Wiring: 




HVAC: 



The bathtubs were put in too..



Here are few pics from the outside again..



They say at this point everything goes pretty quickly! Looking forward for next weekend to see the changes..